Project: 6,5 MW PV plant execution design.
Client: LT (the EPC) has many years of experience and consolidated tracke record in EPC and O&M with more that 500 MW installed and 1,3 GW under O&M. Nadara (the final Client) is a significant player in the renewable energy sector. Formed from the merger of Ventient Energy and Renantis, Nadara is now the largest independent producer of onshore wind energy in Europe. The company owns more than 4,2 GW of installed capacity.
Activities: SunGAP assisted the Client in identifying the optimal technical solution for building the 6,5 MW plant, specifically focusing on the executive engineering of the facility. The goal was to meet both regulatory and final client requirements while maximizing revenue, minimizing construction time, ensuring the highest quality, and establishing a new best practice in the industry.